NRS 108.233
Duration of lien.


1.

A lien provided for in NRS 108.221 to 108.246, inclusive, must not bind the property subject to the lien for a period longer than 6 months after the date on which the notice of lien was recorded, unless:

(a)

Proceedings are commenced in a proper court within that time to enforce the same; or

(b)

The time to commence the action is extended by a written instrument signed by the lien claimant and by a person or persons in interest in the property subject to the lien, in which event, and as to only that person or those persons in interest signing the agreement, the time is extended, but no extension is valid unless in writing and recorded in the county recorder’s office in which the notice of lien is recorded and unless the extension agreement is recorded within the 6-month period. The extension agreement, to be recorded, must be acknowledged as required by law for the acknowledgment of deeds. An action may be commenced within the extended time only against the persons signing the extension agreement and only as to their interests in the property are affected, and upon the lapse of the time specified in the extension agreement, an action may not thereafter be commenced, nor may a second extension be given.

2.

For all purposes, a notice of lien shall be deemed to have expired as a lien against the property after the lapse of the 6-month period provided in subsection 1, and the recording of a notice of lien does not provide actual or constructive notice after the lapse of the 6-month period and as a lien on the property referred to in the notice of lien, unless, before the lapse of the 6-month period an extension agreement has been recorded, in which event, the lien will only continue as a lien on the interests of those persons signing the extension for the period specified in the extension. An extension must not be given for a period in excess of 1 year beyond the date on which the notice of lien is recorded.

3.

If there are other notices of lien outstanding against the property, an extension must not be given upon a notice of lien which will tend to delay or postpone the collection of other liens evidenced by a notice of lien or encumbrances against the property.

Source: Section 108.233 — Duration of lien., https://www.­leg.­state.­nv.­us/NRS/NRS-108.­html#NRS108Sec233.

108.221
Definitions.
108.222
Lien on property, improvements and construction disbursement account
108.225
Priority of liens.
108.226
Perfection of lien: Time for recording notice of lien
108.227
Service of copy of notice of lien.
108.228
Notice of completion: Recording
108.229
Recording and service of amended notice of lien
108.231
Notice of lien against two or more separate buildings or mining claims: Designation of amount due on each
108.232
Notice of lien to be recorded
108.233
Duration of lien.
108.234
Recording of notice of nonresponsibility by disinterested owner
108.235
Amount recoverable by prime contractor
108.236
Court must declare rank of lien claimants or class of lien claimants
108.237
Award of lienable amount, cost of preparing and recording notice of lien, costs of proceedings and representation and other amounts to prevailing lien claimant
108.238
Right to maintain civil action or submit controversy to arbitration not impaired.
108.239
Action to enforce notice of lien: Complaint
108.243
Assignment of lien.
108.244
Limitation on filing complaint for foreclosure of notice of lien.
108.245
Notice of right to lien: Form
108.2212
“Contract” defined.
108.2214
“Lien claimant” defined.
108.2216
“Prime contract” defined.
108.2218
“Surety bond” defined.
108.2275
Frivolous or excessive notice of lien: Motion
108.2403
Lessee to record notice of posted security and either establish construction disbursement account or record surety bond before beginning work of improvement
108.2407
Lien claimant has lien upon funds in construction disbursement account
108.2413
Release of lien rights or notice of lien by posting surety bond.
108.2415
Form of surety bond posted to release lien
108.2421
Action against principal and surety on surety bond and debtor: Action before or after surety bond is recorded
108.2423
Enforcement of liability of principal and surety.
108.2425
Exception to sufficiency of surety or surety bond
108.2433
Discharge of notice of lien: Marginal entries
108.2437
Discharge of notice of lien: Recording by lien claimant
108.2457
Term of contract that attempts to waive or impair lien rights of contractor, subcontractor or supplier void
108.22104
“Agent of the owner” defined.
108.22108
“Building” defined.
108.22112
“Commencement of construction” defined.
108.22116
“Completion of the work of improvement” defined.
108.22118
“Construction control” defined.
108.22124
“Equipment” defined.
108.22128
“Improvement” defined.
108.22132
“Lien” defined.
108.22136
“Lienable amount” defined.
108.22144
“Material” defined.
108.22146
“Notice of lien” defined.
108.22148
“Owner” defined.
108.22156
“Prevailing lien claimant” defined.
108.22164
“Prime contractor” defined.
108.22168
“Principal” defined.
108.22172
“Property” defined.
108.22176
“Surety” defined.
108.22184
“Work” defined.
108.22188
“Work of improvement” defined.
Last Updated

Jun. 24, 2021

§ 108.233’s source at nv​.us