NRS 108.228
Notice of completion: Recording

  • contents
  • verification
  • delivery of copy to each prime contractor and potential lien claimant
  • effect of failure to deliver copy to prime contractor or lien claimant.

1.

The owner may record a notice of completion after the completion of the work of improvement.

2.

The notice of completion must be recorded in the office of the county recorder of the county where the property is located and must set forth:

(a)

The date of completion of the work of improvement.

(b)

The owner’s name or owners’ names, as the case may be, the address of the owner or addresses of the owners, as the case may be, and the nature of the title, if any, of the person signing the notice.

(c)

A description of the property sufficient for identification.

(d)

The name of the prime contractor or names of the prime contractors, if any.

3.

The notice must be verified by the owner or by some other person on the owner’s behalf. The notice need not be acknowledged to be recorded.

4.

Upon recording the notice pursuant to this section, the owner shall, within 10 days after the notice is recorded, deliver a copy of the notice by certified mail, to:

(a)

Each prime contractor with whom the owner contracted for all or part of the work of improvement.

(b)

Each potential lien claimant who, before the notice was recorded pursuant to this section, either submitted a request to the owner to receive the notice or delivered a preliminary notice of right to lien pursuant to NRS 108.245.

5.

The failure of the owner to deliver a copy of the notice of completion in the time and manner provided in this section renders the notice of completion ineffective with respect to each prime contractor and lien claimant to whom a copy was required to be delivered pursuant to subsection 4.

Source: Section 108.228 — Notice of completion: Recording; contents; verification; delivery of copy to each prime contractor and potential lien claimant; effect of failure to deliver copy to prime contractor or lien claimant., https://www.­leg.­state.­nv.­us/NRS/NRS-108.­html#NRS108Sec228.

108.221
Definitions.
108.222
Lien on property, improvements and construction disbursement account
108.225
Priority of liens.
108.226
Perfection of lien: Time for recording notice of lien
108.227
Service of copy of notice of lien.
108.228
Notice of completion: Recording
108.229
Recording and service of amended notice of lien
108.231
Notice of lien against two or more separate buildings or mining claims: Designation of amount due on each
108.232
Notice of lien to be recorded
108.233
Duration of lien.
108.234
Recording of notice of nonresponsibility by disinterested owner
108.235
Amount recoverable by prime contractor
108.236
Court must declare rank of lien claimants or class of lien claimants
108.237
Award of lienable amount, cost of preparing and recording notice of lien, costs of proceedings and representation and other amounts to prevailing lien claimant
108.238
Right to maintain civil action or submit controversy to arbitration not impaired.
108.239
Action to enforce notice of lien: Complaint
108.243
Assignment of lien.
108.244
Limitation on filing complaint for foreclosure of notice of lien.
108.245
Notice of right to lien: Form
108.2212
“Contract” defined.
108.2214
“Lien claimant” defined.
108.2216
“Prime contract” defined.
108.2218
“Surety bond” defined.
108.2275
Frivolous or excessive notice of lien: Motion
108.2403
Lessee to record notice of posted security and either establish construction disbursement account or record surety bond before beginning work of improvement
108.2407
Lien claimant has lien upon funds in construction disbursement account
108.2413
Release of lien rights or notice of lien by posting surety bond.
108.2415
Form of surety bond posted to release lien
108.2421
Action against principal and surety on surety bond and debtor: Action before or after surety bond is recorded
108.2423
Enforcement of liability of principal and surety.
108.2425
Exception to sufficiency of surety or surety bond
108.2433
Discharge of notice of lien: Marginal entries
108.2437
Discharge of notice of lien: Recording by lien claimant
108.2457
Term of contract that attempts to waive or impair lien rights of contractor, subcontractor or supplier void
108.22104
“Agent of the owner” defined.
108.22108
“Building” defined.
108.22112
“Commencement of construction” defined.
108.22116
“Completion of the work of improvement” defined.
108.22118
“Construction control” defined.
108.22124
“Equipment” defined.
108.22128
“Improvement” defined.
108.22132
“Lien” defined.
108.22136
“Lienable amount” defined.
108.22144
“Material” defined.
108.22146
“Notice of lien” defined.
108.22148
“Owner” defined.
108.22156
“Prevailing lien claimant” defined.
108.22164
“Prime contractor” defined.
108.22168
“Principal” defined.
108.22172
“Property” defined.
108.22176
“Surety” defined.
108.22184
“Work” defined.
108.22188
“Work of improvement” defined.
Last Updated

Jun. 24, 2021

§ 108.228’s source at nv​.us