NRS 108.227
Service of copy of notice of lien.


1.

In addition to the requirements of NRS 108.226, a copy of the notice of lien must be served upon the owner of the property within 30 days after recording the notice of lien, in one of the following ways:

(a)

By personally delivering a copy of the notice of lien to the owner or registered agent of the owner;

(b)

By mailing a copy of the notice of lien by certified mail, return receipt requested, to the owner at the owner’s place of residence or the owner’s usual place of business or to the registered agent of the owner at the address of the registered agent; or

(c)

If the place of residence or business of the owner and the address of the registered agent of the owner, if applicable, cannot be determined, by:

(1)

Fixing a copy of the notice of lien in a conspicuous place on the property;

(2)

Delivering a copy of the notice of lien to a person there residing, if such a person can be found; and

(3)

Mailing a copy of the notice of lien addressed to the owner at:
(I) The place where the property is located;
(II) The address of the owner as identified in the deed;
(III) The address identified in the records of the office of the county assessor; or
(IV) The address identified in the records of the county recorder of the county in which the property is located.

2.

If there is more than one owner, failure to serve a copy of the notice of lien upon a particular owner does not invalidate a notice of lien if properly served upon another owner.

3.

Each subcontractor who participates in the construction, improvement, alteration or repair of a work of improvement shall deliver a copy of each notice of lien required by NRS 108.226 to the prime contractor. The failure of a subcontractor to deliver the notice to the prime contractor is a ground for disciplinary proceedings pursuant to chapter 624 of NRS.

Source: Section 108.227 — Service of copy of notice of lien., https://www.­leg.­state.­nv.­us/NRS/NRS-108.­html#NRS108Sec227.

108.221
Definitions.
108.222
Lien on property, improvements and construction disbursement account
108.225
Priority of liens.
108.226
Perfection of lien: Time for recording notice of lien
108.227
Service of copy of notice of lien.
108.228
Notice of completion: Recording
108.229
Recording and service of amended notice of lien
108.231
Notice of lien against two or more separate buildings or mining claims: Designation of amount due on each
108.232
Notice of lien to be recorded
108.233
Duration of lien.
108.234
Recording of notice of nonresponsibility by disinterested owner
108.235
Amount recoverable by prime contractor
108.236
Court must declare rank of lien claimants or class of lien claimants
108.237
Award of lienable amount, cost of preparing and recording notice of lien, costs of proceedings and representation and other amounts to prevailing lien claimant
108.238
Right to maintain civil action or submit controversy to arbitration not impaired.
108.239
Action to enforce notice of lien: Complaint
108.243
Assignment of lien.
108.244
Limitation on filing complaint for foreclosure of notice of lien.
108.245
Notice of right to lien: Form
108.2212
“Contract” defined.
108.2214
“Lien claimant” defined.
108.2216
“Prime contract” defined.
108.2218
“Surety bond” defined.
108.2275
Frivolous or excessive notice of lien: Motion
108.2403
Lessee to record notice of posted security and either establish construction disbursement account or record surety bond before beginning work of improvement
108.2407
Lien claimant has lien upon funds in construction disbursement account
108.2413
Release of lien rights or notice of lien by posting surety bond.
108.2415
Form of surety bond posted to release lien
108.2421
Action against principal and surety on surety bond and debtor: Action before or after surety bond is recorded
108.2423
Enforcement of liability of principal and surety.
108.2425
Exception to sufficiency of surety or surety bond
108.2433
Discharge of notice of lien: Marginal entries
108.2437
Discharge of notice of lien: Recording by lien claimant
108.2457
Term of contract that attempts to waive or impair lien rights of contractor, subcontractor or supplier void
108.22104
“Agent of the owner” defined.
108.22108
“Building” defined.
108.22112
“Commencement of construction” defined.
108.22116
“Completion of the work of improvement” defined.
108.22118
“Construction control” defined.
108.22124
“Equipment” defined.
108.22128
“Improvement” defined.
108.22132
“Lien” defined.
108.22136
“Lienable amount” defined.
108.22144
“Material” defined.
108.22146
“Notice of lien” defined.
108.22148
“Owner” defined.
108.22156
“Prevailing lien claimant” defined.
108.22164
“Prime contractor” defined.
108.22168
“Principal” defined.
108.22172
“Property” defined.
108.22176
“Surety” defined.
108.22184
“Work” defined.
108.22188
“Work of improvement” defined.
Last Updated

Jun. 24, 2021

§ 108.227’s source at nv​.us