NRS 278.5693
Requirements for adjustment of boundary line or transfer of land involving adjacent property.


1.

For a boundary line to be adjusted or for land to be transferred pursuant to paragraph (c) of subsection 5 of NRS 278.461, a professional land surveyor must have performed a field survey, set monuments and filed a record of survey pursuant to NRS 625.340.

2.

A record of survey filed pursuant to subsection 1 must contain:

(a)

A certificate by the professional land surveyor who prepared the map stating that:

(1)

He or she has performed a field survey sufficient to locate and identify properly the proposed boundary line adjustment;

(2)

All corners and angle points of the adjusted boundary line have been defined by monuments or will be otherwise defined on a document of record as required by NRS 625.340; and

(3)

The map is not in conflict with the provisions of NRS 278.010 to 278.630, inclusive.

(b)

A certificate that is executed and acknowledged by each affected owner of the abutting parcels which states that:

(1)

The owner has examined the plat and approves and authorizes the recordation thereof;

(2)

The owner agrees to execute the required documents creating any easement which is shown;

(3)

The owner agrees to execute the required documents abandoning any existing easement pursuant to the provisions of NRS 278.010 to 278.630, inclusive;

(4)

All property taxes on the land for the fiscal year have been paid; and

(5)

Any lender with an impound account for the payment of taxes has been notified of the adjustment of the boundary line or the transfer of the land.

(c)

A certificate by the governing body or its designated representative approving the adjustment of the boundary line.

Source: Section 278.5693 — Requirements for adjustment of boundary line or transfer of land involving adjacent property., https://www.­leg.­state.­nv.­us/NRS/NRS-278.­html#NRS278Sec5693.

Last Updated

Feb. 5, 2021

§ 278.5693’s source at nv​.us