NRS 11.208
Action by contractor against Department of Transportation upon contract for construction, reconstruction, improvement or maintenance of highway.


An action by a contractor against the Department of Transportation upon a contract for the construction, reconstruction, improvement or maintenance of a highway must be commenced within 3 years after the date of the:

1.

Completion of the contract; or

2.

Determination of the engineer or decision of the Board of Directors of the Department of Transportation on an appeal of a claim arising from the contract as provided in the standard specifications for construction of roads and bridges adopted by the Department,
Ê whichever occurs later.

Source: Section 11.208 — Action by contractor against Department of Transportation upon contract for construction, reconstruction, improvement or maintenance of highway., https://www.­leg.­state.­nv.­us/NRS/NRS-011.­html#NRS011Sec208.

Last Updated

Feb. 5, 2021

§ 11.208’s source at nv​.us