NRS 704.8905
Grant or denial of application: Time within which Commission and other permitting entities must act

  • determination upon record
  • terms, conditions and modifications
  • service of Commission order.

1.

Except as otherwise required to comply with federal law:

(a)

Not later than 150 days after a person has filed an application regarding a utility facility pursuant to subsection 1 of NRS 704.870:

(1)

The Commission shall grant or deny approval of that application; and

(2)

Each other permitting entity shall, if an application for a permit, license or other approval for the construction of the utility facility was filed with the other permitting entity on or before the date on which the applicant filed the application pursuant to subsection 1 of NRS 704.870, grant or deny the application filed with the other permitting entity.

(b)

Not later than 120 days after a person has filed an application regarding a utility facility pursuant to subsection 2 of NRS 704.870:

(1)

The Commission shall grant or deny approval of the application; and

(2)

Each other permitting entity shall, if an application for a permit, license or other approval for the construction of the utility facility was filed with the other permitting entity on or before the date on which the applicant filed with the appropriate federal agency an application for approval for the construction of the utility facility, grant or deny the application filed with the other permitting entity.

2.

The Commission or other permitting entity shall make its determination upon the record and may grant or deny the application as filed, or grant the application upon such terms, conditions or modifications of the construction, operation or maintenance of the utility facility as the Commission or other permitting entity deems appropriate.

3.

The Commission shall serve a copy of its order and any opinion issued with it upon each party to the proceeding before the Commission.

Source: Section 704.8905 — Grant or denial of application: Time within which Commission and other permitting entities must act; determination upon record; terms, conditions and modifications; service of Commission order., https://www.­leg.­state.­nv.­us/NRS/NRS-704.­html#NRS704Sec8905.

704.820
Short title.
704.825
Declaration of legislative findings and purpose.
704.830
Definitions.
704.834
“Appropriate federal agency” defined.
704.840
“Commence to construct” defined.
704.842
“Environmental review” defined.
704.845
“Local government” defined.
704.848
“Other permitting entity” defined.
704.850
“Person” defined.
704.855
“Public utility” and “utility” defined.
704.860
“Utility facility” defined.
704.863
Applicability.
704.865
Permit required to construct utility facility
704.870
Requirements for filing application: Form and contents
704.871
Approval of application for utility facility not intended to serve customers in State.
704.873
Commission has exclusive jurisdiction to determine need for utility facilities of certain public utilities
704.875
Review of application by Division of Environmental Protection of State Department of Conservation and Natural Resources.
704.877
Duty to accept and incorporate findings and conclusions of environmental review that already has been conducted
704.880
Power of Commission to dispense with hearing for certain applications
704.885
Parties to proceeding for permit
704.890
Grant or denial of permit: Required findings
704.891
Reports to be filed with Commission by person holding permit who is not public utility.
704.893
Limitations on purchase of capacity of utility facility by certain public utilities.
704.895
Rehearing
704.897
Effect of provisions on jurisdiction of Commission over public utilities serving retail customers in State.
704.900
Cooperation with other states and Federal Government.
704.8905
Grant or denial of application: Time within which Commission and other permitting entities must act
Last Updated

Feb. 5, 2021

§ 704.8905’s source at nv​.us