NRS 704.7878
Electric utility required to recover certain amounts through deferred energy accounting adjustment application.


Notwithstanding any other provision of this chapter, an electric utility that enters into a contract with a participant pursuant to NRS 704.7877 shall, in the manner provided pursuant to the regulations adopted by the Commission pursuant to paragraph (c) of subsection 1 of NRS 704.7881, recover through a deferred energy accounting adjustment application an amount equal to the discount provided to the participant pursuant to the contract.

Source: Section 704.7878 — Electric utility required to recover certain amounts through deferred energy accounting adjustment application., https://www.­leg.­state.­nv.­us/NRS/NRS-704.­html#NRS704Sec7878.

Last Updated

Feb. 5, 2021

§ 704.7878’s source at nv​.us