NRS 704.744
Utility required to provide overview of plan or amendment to plan to certain persons before filing such plan or amendment.


The Commission shall require each utility which supplies electricity in this State, not less than 4 months before filing a plan required pursuant to NRS 704.741, or within a reasonable period before filing an amendment to such a plan pursuant to NRS 704.751, to meet with personnel from the Commission and the Bureau of Consumer Protection in the Office of the Attorney General and any other interested persons to provide an overview of the anticipated filing or amendment.

Source: Section 704.744 — Utility required to provide overview of plan or amendment to plan to certain persons before filing such plan or amendment., https://www.­leg.­state.­nv.­us/NRS/NRS-704.­html#NRS704Sec744.

Last Updated

Feb. 5, 2021

§ 704.744’s source at nv​.us