NRS 338.570
Contractor to provide notice concerning progress payments and retainage payments to certain subcontractors and suppliers.


Within 5 working days after a contractor receives a written request from a subcontractor or supplier of his or her subcontractor or supplier with respect to a subcontract which has not been fully performed, the contractor shall notify the subcontractor or supplier of his or her subcontractor or supplier in writing of the following:

1.

The date the contractor made a specified progress payment or retainage payment to his or her subcontractor or supplier;

2.

Whether the contractor has paid the entire amount of a specified progress payment or retainage payment to his or her subcontractor or supplier; and

3.

The amount withheld by the contractor from a specified progress payment or retainage payment to his or her subcontractor or supplier, if any.
Payments Made by Subcontractor to Subcontractors and Suppliers

Source: Section 338.570 — Contractor to provide notice concerning progress payments and retainage payments to certain subcontractors and suppliers., https://www.­leg.­state.­nv.­us/NRS/NRS-338.­html#NRS338Sec570.