NRS 338.1723
Advertisement for preliminary proposals.
1.
A public body shall advertise for preliminary proposals for the design and construction of a public work by a design-build team. The advertisement must be published:(a)
In a newspaper qualified pursuant to chapter 238 of NRS that is published in the county where the public work will be performed at least once and not less than 7 days before the opening of bids; and(b)
On the Internet website of the public body, if the public body maintains an Internet website, every day for not less than 7 days before the opening of bids.2.
A request for preliminary proposals published pursuant to subsection 1 must include, without limitation:(a)
A description of the public work to be designed and constructed;(b)
An estimate of the cost to design and construct the public work;(c)
The dates on which it is anticipated that the separate phases of the design and construction of the public work will begin and end;(d)
The date by which preliminary proposals must be submitted to the public body;(e)
If the proposal is for a public work of the State, a statement setting forth that the prime contractor must be qualified to bid on a public work of the State pursuant to NRS 338.1379 before submitting a preliminary proposal;(f)
A description of the extent to which designs must be completed for both preliminary and final proposals and any other requirements for the design and construction of the public work that the public body determines to be necessary;(g)
A list of the requirements set forth in NRS 338.1721;(h)
A list of the factors and relative weight assigned to each factor that the public body will use to evaluate design-build teams who submit a proposal for the public work;(i)
Notice that a design-build team desiring to submit a proposal for the public work must include with its proposal the information used by the public body to determine finalists among the design-build teams submitting proposals pursuant to subsection 2 of NRS 338.1725 and a description of that information; and(j)
A statement as to whether a design-build team that is selected as a finalist pursuant to NRS 338.1725 but is not awarded the design-build contract pursuant to NRS 338.1727 will be partially reimbursed for the cost of preparing a final proposal and, if so, an estimate of the amount of the partial reimbursement.
Source:
Section 338.1723 — Advertisement for preliminary proposals., https://www.leg.state.nv.us/NRS/NRS-338.html#NRS338Sec1723
.